Project
Description:
The
Keo Way interchange will be reconstructed. Work will be
completed in stages with reconstruction work on the north
side of I-235 beginning in Mid Sept. 2004. The exit and
entrance ramps in this area will be rebuilt.
Project Schedule: Mid Sept. 2004 - Dec. 2006

|
Stage 1:
Mid Sept. 2004 - summer 2005 - The westbound exit
ramps to Keo Way north and south will be reconstructed.
A new westbound ramp bridge will be built over
Keo Way.
Stage 2:
Summer 2005 - Dec. 2006 - The eastbound exit and
entrance ramps will be reconstructed. New mainline
bridges will also be built in the interchange
area.
|
Traffic
Impacts: Stage 1
The
westbound exit ramp to Keo Way north will be closed.
The
westbound exit loop to Keo Way south will be closed.
The
entrance ramp to eastbound I-235 will be closed.
The suggested alternate routes will be the 19th St./MLK
Jr. Pkwy interchange and the 2nd/3rd interchange.
Detour
maps:
To
Keo Way from westbound I-235
To
I-235 eastbound from Keo Way
|