63rd Street (Iowa 28) Interchange
|
NOTE: The 63rd St. Bridge and ramps are now completed.
Project
Description:
Reconstruction of this interchange began in Aug. 2004.
The first phase involved building the east half of the
new bridge and interchange, which was completed in Nov.
2004. The second phase involves building the west half
of the bridge and should be completed by mid-summer 2005.
Project Schedule: July 2004 - summer 2005
Traffic
Impacts:
One
lane of traffic in each direction will be maintained
on 63rd Street through the construction area.
The
entrance and exit ramps will be closed periodically during the project.
|