Downtown Interchange Reconstruction


Note: The downtown interchange reconstruction project has been completed.

Project Description:
The 3rd Street eastbound off-ramp and the 5th Street on-ramp will be reconstructed.  This work also includes the construction of a new 5th Street eastbound entrance ramp bridge over the 3rd Street off-ramp. This construction will provide separation of eastbound exiting traffic at 3rd Street from freeway traffic entering at 5th Street.
 

Traffic Impacts :


3rd Street eastbound off-ramp will be closed
5th Street on-ramp will be closed

Project Schedule:


3rd Street eastbound off-ramp: January - November 2007
5th Street on-ramp: Fall 2005 - November 2007

Maps:

Suggested routes from I-235 to downtown
Suggested routes to I-235 from downtown

Downtown Interchange project map

map legend

 

Mainline and interchange work. Mainline I-235 will be reconstructed from Cottage Grove to east of DM River. The Keo Way interchange will be reconstructed.
Mainline construction
This project involves mainline reconstruction from east of the DM River to E. 15th St..
Mainline and bridge construction
Mainline I-235 will be rebuilt and the bridges at Guthrie, Hull and Broadway will be reconstructed.
   