GENERAL INFORMATION
When was I-235 originally built?
It was designed in the 1950s and constructed
in the 1960s.
Why must I-235 be rebuilt?
- Safety is the primary reason. I-235 has
a higher than average crash rate. The crash toll continues to
rise, averaging 850 collisions per year along the entire length,
including the 21 interchanges. The new freeway could save lives
and head off serious accidents.
- I-235 wasn’t designed to handle the current
traffic. When the freeway was designed in the 1950s, it was predicted
that by 1975 about 20,000 vehicles per day (vpd) would use the
road in West Des Moines and that the daily traffic count would
hit 77,000 vpd in the middle of Des Moines. The reality is that
daily freeway traffic in West Des Moines now exceeds 80,000 and
it increases to 110,000 vehicles from 56th to 42nd streets in
Des Moines. Traffic projections indicate the counts could exceed
150,000 vpd.
- Even with improvements to city streets
and other state highways, the area can’t handle the projected
traffic over the next 20 years.
- The pavement is over 30-years old and
the freeway is wearing out.
- Bridges over I-235 are lower than modern
standards, resulting in trucks hitting bridges causing congestion,
structural damage to the bridges and possible injuries.
How much will construction cost?
It will cost approximately $429 million.
SCHEDULE
When will construction take place?
Construction got underway in 2002 and will
continue through 2007. This was phased to allow bridge and interchange
work to begin in 2002. Reconstruction and paving of the freeway
lanes takes place in 2004.
What’s the construction timeline year-by-year?
2002- utility relocation, bridge replacement,
interchange reconstruction
2003- bridge replacement, interchange reconstruction
2004- bridge widening and replacement, interchange
reconstruction, mainline paving
2005- mainline paving, bridge replacement
2006- mainline paving, bridge replacement
2007- mainline paving, bridge replacement
Why is the project taking six years? Can’t
it be done faster?
The project is phased to allow the maximum
amount of work per construction season, with minimal delay and inconvenience.
For example, if multiple consecutive interchanges were reconstructed
at the same time, it might accelerate the schedule but it would
reduce the access to I-235 causing inconvenience and possible safety
concerns.
Back to top
IMPACTS
When will the most traffic congestion/delays
occur?
It’s expected that traffic congestion and
delays will become more significant when mainline paving begins
and work forces the freeway down to two lanes in each direction.
This will begin in 2004 when work on mainline I-235 starts on the
western portions of the freeway. This will reduce capacity significantly.
However, freeway lanes will always be open and we will not schedule
the closure of two consecutive interchanges.
What time of day will construction work
be done? Will work be done at night?
The majority of the work is planned for during
the day, however there will be times when night construction is
necessary.
Are there homes in the project right of
way?
In order to construct the much-needed improvements,
additional right-of-way is needed in some areas. Unfortunately,
some residential acquisitions are necessary to improve the safety
and operation of I-235. We have made some refinements to the design
in an effort to minimize the impacts to properties.
What will be done to relieve congestion
and traffic delays?
There will be a variety of solutions
available that could impact congestion and delays. The goal will
be to reduce I-235 traffic by 10 percent during peak periods. Drivers
will be encouraged to use alternative transportation means like
bus, carpools and vanpools. Businesses will be encouraged to provide
bus passes, implement flexible schedules, and allow workers to telecommute
when possible. Alternative transportation routes will be identified
and publicized.
How can I get information on how to ride
the bus?
Transit information can be found by accessing
the Des Moines Metropolitan Transit Authority (MTA) Web site at
http://www.dmmta.com or by phoning
MTA at (515) 283-8141.
Back to top
MORE INFORMATION
Will there be one place to get information
on the project?
Yes! There will be a variety of ways to get
one-stop information on I-235 reconstruction. I235.com is the best
source for current information.
Beginning in the spring of 2003 motorists
will also be able to dial 511 to obtain up-to-date information on
I-235 closures and other construction work that may affect travel.
How will I be able to find out about construction
near my home or business? Will the DOT give us advanced notice of
closures?
We will use a number of ways to communicate
important information about how the reconstruction may affect you
when the construction begins. Planned closures will be reported
on local radio and television media, newspapers and many employee
communications. The Web site will provide real-time information
on rapidly changing information, alternate routes, transportation
alternatives as well as closure notices and much more.