2003 PROJECTS
|
| |
| |
Valley
West Drive Bridge and all ramps are now open.
Description:
The
interchange was reconstructed and the bridge over
I-235 replaced. The reconstructed interchange includes
a new ramp for northbound traffic on Valley West
Drive (VWD) entering eastbound
I-235. A noise wall was constructed on the south
side of the freeway between 33rd and 28th streets
in West Des Moines. Closure
Schedule: March 31, 2003 to November 14, 2003.
Valley West Drive was closed to traffic at the freeway
while the new bridge was constructed.
|
|
Construction of the ramps serving this interchange were
staged so some access could be maintained during various
stages of construction. Ramps under construction were
typically closed six to eight weeks,  |
|
|
|
|