Project
Description:
Mainline
traffic lanes will be rebuilt from the west interchange
of I-35/80/235 to the 8th St/73rd St interchange. When
completed there will be three lanes in each direction.
The
I-235 bridges over 22nd Street and 17th Street will be
widened. Project
Schedule: March 2004 - December 2004
The bridges have been widened. The work remaining includes
construction of the barrier rail in the median.
Traffic
Impacts:
Two
lanes of traffic in each direction will be maintained
on I-235 during peak driving times.
|